Release code: Rel-16
Status: Frozen
Release name: Release 16
Release description: -
Release short name: Rel-16
Start date: 2017-03-22
End date: SA#88-e 2020-07-03
Closure date: - -
Remarks (2)
Creation dateAuthorRemark
2020-03-23 15:28 UTC
John M Meredith
Further three month delay due to coronavirus disruption of F2F meetings.
2019-01-22 09:29 UTC
John M Meredith
RAN#82: Three month delay to stage 3 target.
Follows Release:
ITUR code:
Versions
2G: 2G Decimal:
3G: 3G Decimal:
WPM codes
2G:
3G:
Action dateActionAuthor
2017-03-22 16:48 UTC
Release created.
John M Meredith
2017-09-15 04:35 UTC
Release updated. Changes:
End date: (None) => (None)
John M Meredith
2018-01-02 12:04 UTC
Release updated. Changes:
End date: (None) => 2020-12-20 (SA#87-dates TBC)
John M Meredith
2018-03-26 13:23 UTC
Release updated. Changes:
End date: 2020-12-20 (SA#87-dates TBC) => 2019-12-13 (SA#86)
Mathieu Mangion
2018-03-26 13:23 UTC
Release updated. Changes:
End date: 2019-12-13 (SA#86) => 2020-03-20 (SA#87-dates TBC)
Mathieu Mangion
2019-01-22 09:28 UTC
Release updated. Changes:
End date: 2020-03-20 (SA#87) => 2020-06-19 (SA#88)
John M Meredith
2020-07-03 14:29 UTC
Release updated. Changes:
End date: 2020-06-19 (SA#88) => 2020-07-03 (SA#88-e)
John M Meredith
2020-07-07 10:09 UTC
Release frozen.
John M Meredith
2020-07-07 10:09 UTC
Release frozen.
John M Meredith