WI # 750028 - 5GS_Ph1-CT
Name: CT4 aspects of 5G System - Phase 1
Acronym: 5GS_Ph1-CT
Effective Acronym: 5GS_Ph1-CT
WI Level: Work Task (3rd Level)
Type: Work Item
Status: PCG approved
Release: Rel-15
Start date: 2017-03-03
End date: 2017-12-14
Remarks (7)
Creation dateAuthorRemark
2019-01-18 09:29 UTC
10/12/18: 99%->100
2018-09-25 14:16 UTC
10/9/18: 95%->99
2018-06-07 14:37 UTC
7/6/18: 50%->95
2018-03-16 10:42 UTC
16/3/18: 45%->50
2017-12-15 15:57 UTC
15/12/17: 25%->45
2017-09-11 02:08 UTC
11/9/17: 5%->25
2017-06-13 08:15 UTC
5/6/17: 0%->5
Parent Work Item: 750025 - CT aspects of 5G System - Phase 1
Child Work Items:
WI UIDWI name
No records to display.
Responsible group(s): C4
Rapporteur(s): Landais, Bruno (Nokia)
Latest WID version: CP-183243
TSG Approval meeting: 75
PCG Approval meeting: 38
TSG Stopped meeting: -
PCG Stopped meeting: -
See Specifications specifically resulting from this Work Item
See all related Change Requests related to this Work Item (all specifications)