WI # 800019 - eMCSMI
Name: Enhanced Mission Critical System Migration and Interconnection
Acronym: eMCSMI
Effective Acronym: eMCSMI
WI Level: Feature (1st level)
Type: Work Item
Status: PCG approved
Release: Rel-16
Start date: 2018-06-06
End date: 2019-06-12
Remarks (4)
Creation dateAuthorRemark
2019-06-13 07:06 UTC
7/12/18: 5%->10¦7/12/18: FCD:03/19->06/19¦; 31/5/19: 50%->100
2019-03-29 15:42 UTC
14/3/19: 10%->50
2018-12-07 15:36 UTC
7/12/18: 5%->10; 7/12/18: FCD:03/19->06/19
2018-09-25 14:16 UTC
10/9/18: 0%->5
Parent Work Item: None
Child Work Items:
WI UIDWI name
No records to display.
Responsible group(s): S6
Rapporteur(s): david.chater-lea@motorolasolutions.com (Chater-Lea, David; Motorola Solutions)
Latest WID version: SP-180379
TSG Approval meeting: 80
PCG Approval meeting: 41
TSG Stopped meeting: -
PCG Stopped meeting: -
See Specifications specifically resulting from this Work Item